Sorry if it's not being very clear:

The retention section is not deprecated.

What is deprecated is scheduling the retention on its own.

So, the way it works is:

  • you can schedule a backup followed by a retention (in the same schedule)
  • you can schedule a forget. Typically a scheduled forget can have different options than the retention section.